Grumman and NASA announced the selection of four companies as major LEM subcontractors:
Aviation Daily reported an announcement by Frank Canning, Assistant LEM Project Manager at Grumman, that a Request for Proposals would be issued in about two weeks for the development of an alternate descent propulsion system. Because the descent stage presented what he called the LEM's "biggest development problem," Canning said that the parallel program was essential.
A bidders' conference was held at Grumman for a LEM mechanically throttled descent engine to be developed concurrently with Rocketdyne's helium injection descent engine. Corporations represented were Space Technology Laboratories; United Technology Center, a division of United Aircraft Corporation; Reaction Motors Division, Thiokol Chemical Corporation; and Aerojet-General Corporation. Technical and cost proposals were due at Grumman on April 8.
Grumman reported that it had advised North American's Rocketdyne Division to go ahead with the lunar excursion module descent engine development program. Negotiations were complete and the contract was being prepared for MSC's review and approval. The go-ahead was formally issued on May 2.
Rocketdyne reported to Grumman on the LEM descent stage engine development program. Revised measurements for the engine were: diameter, 137 centimeters (54 inches); length, 221 centimeters (87 inches) (30.5 centimeters (twelve inches) more than the original constraint that Grumman had imposed on Rocketdyne).
Space Technology Laboratories received Grumman's go-ahead to develop the parallel descent engine for the LEM. At the same time, Grumman ordered Bell Aerosystems Company to proceed with the LEM ascent engine. The contracts were estimated at $18,742,820 and $11,205,415, respectively.
At a LEM Mechanical Systems Meeting in Houston, Grumman and MSC agreed upon a preliminary configuration freeze for the LEM-adapter arrangement. The adapter would be a truncated cone, 876 centimeters (345 inches) long. The LEM would be mounted inside the adapter by means of the outrigger trusses on the spacecraft's landing gear. This configuration provided ample clearance for the spacecraft, both top and bottom (i.e., between the service propulsion engine bell and the instrument unit of the S-IVB).
At this same meeting, Grumman presented a comparison of radially and laterally folded landing gears (both of 457-centimeter (180-inch) radius). The radial-fold configuration, MSC reported, promised a weight savings of 22-2 kilograms (49 pounds). MSC approved the concept, with an 876-centimeter (345-inch) adapter. Further, an adapter of that length would accommodate a larger, lateral fold gear (508 centimeters (200 inches)), if necessary. During the next several weeks, Grumman studied a variety of gear arrangements (sizes, means of deployment, stability, and even a "bending" gear). At a subsequent LEM Mechanical Systems Meeting, on November 10, Grumman presented data (design, performance, and weight) on several other four-legged gear arrangements - a 457-centimeter (180-inch), radial fold "tripod" gear (i.e., attached to the vehicle by three struts), and 406.4-centimeter (160-inch) and 457-centimeter (180-inch) cantilevered gears. As it turned out, the 406.4-centimeter (160-inch) cantilevered gear, while still meeting requirements demanded in the work statement, in several respects was more stable than the larger tripod gear. In addition to being considerably lighter, the cantilevered design offered several added advantages:
ASPO Manager Joseph F. Shea asked NASA Headquarters to revise velocity budgets for the Apollo spacecraft. (Studies had indicated that those budgets could be reduced without degrading performance.) He proposed that the 10 percent safety margin applied to the original budget be eliminated in favor of specific allowances for each identifiable uncertainty and contingency; but, to provide for maneuvers which might be desired on later Apollo missions, the LEM's propellant tanks should be oversized.
The ASPO Manager's proposal resulted from experience that had arisen because of unfortunate terminology used to designate the extra fuel. Originally the fuel budget for various phases of the mission had been analyzed and a 10 percent allowance had been made to cover - at that time, unspecified - contingencies, dispersions, and uncertainties. Mistakenly this fuel addition became known as a "10% reserve"! John P. Mayer and his men in the Mission Planning and Analysis Division worried because engineers at North American, Grumman, and NASA had "been freely 'eating' off the so-called 'reserve'" before studies had been completed to define what some of the contingencies might be and to apportion some fuel for that specific situation. Mayer wanted the item labeled a "10% uncertainty."
Shea recommended also that the capacity of the LEM descent tanks be sufficient to achieve an equiperiod orbit, should this become desirable. However, the spacecraft should carry only enough propellant for a Hohmann transfer. This was believed adequate, because the ascent engine was available for abort maneuvers if the descent engine failed and because a low altitude pass over the landing site was no longer considered necessary. By restricting lunar landing sites to the area between ±5 degrees latitude and by limiting the lunar stay time to less than 48 hours, a one-half-degree, rather than two-degree, plane change was sufficient.
In the meantime, Shea reported, his office was investigating how much weight could be saved by these propellant reductions.
Grumman selected AiResearch Manufacturing Company to supply cryogenic storage tanks for the LEM electrical power system. Final negotiations on the cost-plus-incentive-fee contract were held in June 1964.
On this same date, Grumman concluded negotiations with Allison Division of General Motors Corporation for design and fabrication of the LEM descent engine propellant storage tanks (at a cost of $5,479,560).
ASPO concurred in Grumman's recommendation to delete the redundant gimbal actuation system in the LEM's descent engine. A nonredundant configuration would normally require mission abort in case of actuator failure. Consequently, in making this change, Grumman must ensure that mission abort and the associated staging operation would not compromise crew survival and mission reliability.
MSC decided to supply television cameras for the LEM as government-furnished items. Grumman was ordered to cease its effort on this component.
Resizing of the LEM propulsion tanks was completed by Grumman. The cylindrical section of the descent tank was extended 34.04 millimeters (1.34 inches), for a total of 36.27 centimeters (14.28 inches) between the spherical end bells. The ascent tanks (two-tank series) were 1240.54 centimeters (48.84 inches) in diameter.
North American, Grumman, and MIT Instrumentation Laboratory summarized results of a six-week study, conducted at ASPO's request, on requirements for a Spacecraft Development Program. Purpose of the study was to define joint contractor recommendations for an overall development test plan within resource constraints set down by NASA. ASPO required that the plan define individual ground test and mission objectives, mission descriptions, hardware requirements (including ground support equipment), test milestones, and individual subsystem test histories.
Intermediate objectives for the Apollo program were outlined: the qualification of a manned CSM capable of earth reentry at parabolic velocities after an extended space mission; qualification of a manned LEM both physically and functionally compatible with the CSM; and demonstration of manned operations in deep space, including lunar orbit. The most significant basic test plan objective formulated during the study was the need for flexibility to capitalize on unusual success or to compensate for unexpected difficulties with minimum impact on the program.
Only one major issue in the test plan remained unresolved - lunar descent radar performance and actual lunar touchdown. Two possible solutions were suggested:
The complete findings of this joint study were contained in a five-volume report issued by North American and submitted to MSC early in February 1964. (This document became known informally as the "Project Christmas Present Report.")
MSC directed Grumman to integrate LEM translation and descent engine thrust controllers. The integrated controller would be lighter and easier to install; also it would permit simultaneous reaction control system translation and descent engine control. Grumman had predicted that such a capability might be required for touchdown.
The first full-throttle firing of Space Technology Laboratories' LEM descent engine (being developed as a parallel effort to the Rocketdyne engine) was carried out. The test lasted 214 seconds, with chamber pressures from 66.2 to 6.9 newtons per square centimeter (96 to 10 psi). Engine performance was about five percent below the required level.
MSC authorized AiResearch Manufacturing Company and the Linde Company to manufacture high- pressure insulated tanks. This hardware, to be available about May 15, would be used in a study of the feasibility of a supercritical helium pressurization system for the LEM.
MSC gave its formal consent to two of Grumman's subcontracts for engines for the LEM: (1) With Bell Aerosystems for the ascent engine ($11,205,416 incentive-fee contract) (2) With Space Technology Laboratories for a descent engine to parallel that being developed by Rocketdyne ($18,742,820 fixed-fee contract).
Representatives from a number of elements within MSC (including systems and structural engineers, advanced systems and rendezvous experts, and two astronauts, Edward H. White II and Elliot M. See, Jr.) discussed the idea of deleting the LEM's front docking capability (an idea spawned by the recent TM-1 mockup review). Rather than nose-to-nose docking, the LEM crew might be able to perform the rendezvous and docking maneuver, docking at the spacecraft's upper (transfer) hatch, by using a window above the LEM commander's head to enable him to see his target. Additional Details: here....
NASA conducted a formal review of the LEM mockup M-5 at the Grumman factory. This inspection was intended to affirm that the M-5 configuration reflected all design requirements and to definitize the LEM configuration. Members of the Mockup Review Board were Chairman Owen E. Maynard, Chief, Systems Engineering Division, ASPO; R. W. Carbee, LEM Subsystem Project Engineer, Grumman; Maxime A. Faget, Assistant Director for Engineering and Development, MSC; Thomas J. Kelly, LEM Project Engineer, Grumman; Christopher C. Kraft, Jr. (represented by Sigurd A. Sjoberg), Assistant Director for Flight Operations, MSC; Owen G. Morris, Chief, Reliability and Quality Assurance Division, ASPO; William F. Rector III, LEM Project Officer, ASPO; and Donald K. Slayton, Assistant Director for Flight Crew Operations, MSC.
The astronauts' review was held on October 5 and 6. It included demonstrations of entering and getting out of the LEM, techniques for climbing and descending the ladder, and crew mobility inside the spacecraft. The general inspection was held on the 7th and the Review Board met on the 8th. Those attending the review used request for change (RFC) forms to propose spacecraft design alterations. Before submission to the Board, these requests were discussed by contractor personnel and NASA coordinators to assess their effect upon system design, interfaces, weight, and reliability.
The inspection categories were crew provisions; controls, displays, and lighting; the stabilization and control system and the guidance and navigation radar; electrical power; propulsion (ascent, descent, reaction control system, and pyrotechnics ; power generation cryogenic storage and fuel cell assemblies ; environmental control; communications and instrumentation; structures and landing gear; scientific equipment; and reliability and quality' control. A total of 148 RFCs were submitted. Most were aimed at enhancing the spacecraft's operational capability; considerable attention also was given to quality and reliability and to ground checkout of various systems. No major redesigns of the configuration were suggested.
As a result of this review, the Board recommended that Grumman take immediate action on those RFC's which it had approved. Further, the LEM contractor and MSC should promptly investigate those items which the Board had assigned for further study. On the basis of the revised M-5 configuration, Grumman could proceed with LEM development and qualification. This updated mockup would be the basis for tooling and fabrication of the initial hardware as well.
MSC's Systems Engineering Division reported on the consequences of eliminating the command and service module (CSM) rendezvous radar:
ASPO Manager Joseph F. Shea informed Apollo Program Director Samuel C. Phillips that it was his desire to review the progress of the two subcontractors (Space Technology Laboratory and Rocketdyne) prior to the final evaluation and selection of a subcontractor for the LEM descent engine.
Shea had asked MSC's Maxime A. Faget to be chairman of a committee to accomplish the review, and would also ask the following individuals to serve: C. H. Lambert, W. F. Rector III, and J. G. Thibodaux, all of MSC; L. F. Belew, MSFC; M. Dandridge and J. A. Gavin, Grumman; I. A. Johnsen, Lewis Research Center; C. H. King, OMSF; Maj. W. R. Moe, Edwards Rocket Research Laboratory; and A. O. Tischler, NASA Office of Advanced Research and Technology.
The Committee should
From MSC, Grumman received updated criteria to be used in the design of the LEM's landing gear. The gear must be designed to absorb completely the landing impact; it must also provide adequate stability for the vehicle under varying surface conditions, which were spelled out in precise detail.) Maximum conditions that MSC anticipated at touchdown were:
vertical velocity - 3.05 m (10 ft) per sec
horizontal velocity - 1.22 m (4 ft) per sec
spacecraft attitude
pitch - 3 degrees
roll - 3 degrees
yaw - random
attitude rates - 3 degrees per sec
At touchdown, all engines (descent and reaction control would be off. "It must be recognized," MSC emphasized, "that the vertical and horizontal velocity values . . . are also constraints on the flight control system."
Grumman ordered its major subcontractors supplying electronic equipment for the LEM to implement revised test programs and hardware schedules (in line with the new design approach). A similar directive went to RCA to modify the attitude and translation and the descent engine control assemblies as required for the new concept of an integrated assembly for guidance, navigation, and control of the spacecraft.
Parallel development of the LEM descent engine was halted. Space Technology Laboratories was named the sole contractor; the Rocketdyne contract was canceled. Grumman estimated that the cost of Rocketdyne's program would be about $25 million at termination.
Evaluations of the three-foot probes on the LEM landing gear showed that the task of shutting off the engine prior to actual touchdown was even more difficult than controlling the vehicle's rate of descent. During simulated landings, about 70 percent of the time the spacecraft was less than 0.3 m (1 ft) high when shutdown came; on 20 percent of the runs, the engine was still burning at touchdown. Some change, either in switch location or in procedure, thus appeared necessary to shorten the delay between contact light and engine cutoff (an average of 0.7 sec).
Grumman reported three major problems with the LEM:
Initial flights of the LLRV interested MSC's Guidance and Control Division because they represented first flight tests of a vehicle with control characteristics similar to the LEM. The Division recommended the following specific items for inclusion in the LLRV flight test program:
MSC's Structures and Mechanics Division was conducting studies of lunar landing conditions. In one study, mathematical data concerning the lunar surface, LEM descent velocity, and physical properties of LEM landing gear and engine skirt were compiled. A computer was programmed with these data, producing images on a video screen, allowing engineers to review hypothetical landings in slow motion.
In another study, a one-sixth scale model of the LEM landing gear was dropped from several feet to a platform which could be adjusted to different slopes. Impact data, gross stability, acceleration, and stroke of the landing gear were recorded. Although the platform landing surface could not duplicate the lunar surface as well as the computer, the drop could verify data developed in the computer program. The results of these studies would aid in establishing ground rules for lunar landings.
An evaluation was made of the feasibility of utilizing a probe-actuated descent engine cutoff light during the LEM lunar touchdown maneuver. The purpose of the light, to be actuated by a probe extending 0.9 m (3 ft) beyond the landing gear pads, was to provide an engine cutoff signal for display to the pilot. Results of the study indicated at least 20 percent of the pilots failed to have the descent engine cut off at the time of lunar touchdown. The high percentage of engine-on landings was attributed to
Grumman officials presented their findings on supercritical versus gaseous oxygen storage systems for the LEM (supercritical: state of homogeneous mixture at a certain pressure and temperature, being neither gas nor liquid). After studying factors of weight, reliability, and thermal control, as well as cost and schedule impacts, they recommended gaseous tanks in the ascent stage and a supercritical tank in the descent stage. They stressed that this configuration would be about 35.66 kg (117 lbs) lighter than an all-gaseous one. Though these spokesmen denied any schedule impact, they estimated that this approach would cost about 2 million more than the all-gaseous mode. MSC was reviewing Grumman's proposal.
During the latter part of the month, Crew Systems Division (CSD) engineers also looked into the several approaches. In contrast to Grumman, CSD calculated that, at most, an all-gaseous system would be but 4.08 kg (9 lbs) heavier than a supercritical one. CSD nonetheless recommended the former. It was felt that the heightened reliability, improved schedules, and "substantial" cost savings that accompanied the all-gaseous approach offset its slim weight disadvantage.
During late April, MSC ordered Grumman to adopt CSD's approach (gaseous systems in both stages of the vehicle). (Another factor involved in this decision was the lessened oxygen requirement that followed substitution of batteries for fuel cells in the LEM.)
William F. Rector, the LEM Project Officer in ASPO, replied to Grumman's weight reduction study (submitted to MSC on December 15, 1964). Rector approved a number of the manufacturer's suggestions:
Grumman and MSC engineers discussed the effect of landing impacts on the structure of the LEM. Based on analyses of critical loading conditions, Grumman reported that the present configuration was inadequate. Several possible solutions were being studied jointly by Grumman and the Structures and Mechanics Division (SMD):
Also Grumman representatives summarized the company's study on the design of the footpads. They recommended that, rather than adopting a stroking-type design, the current rigid footpad should be modified. The modification, they said, would improve performance as much as would the stroking design, without entailing the latter's increased weight and complexity and lowered reliability. SMD was evaluating Grumman's recommendations.
Allison Division of General Motors Corporation completed an analysis of failures in the LEM descent stage's propellant tanks. Investigators placed the blame on brittle forgings. MSC's Propulsion and Power Division reported that "efforts are continuing to insure (that) future forgings will be satisfactory."
As a result of the decision for an all-battery LEM, MSC advised Grumman that power for the entire pre- separation checkout of the spacecraft would be drawn from that module's batteries (instead of only during the 30 minutes prior to separation). This change simplified the electrical mating between the two spacecraft and obviated an additional battery charger in the CSM. From docking until the start of the checkout, however, the CSM would still furnish power to the LEM.
TWX, James L. Neal, MSC, to GAEC, Attn: R. S. Mullaney. April 30, 1965.
During the Month
Grumman reported two major problems with the LEM's descent engine:
A tentative agreement was reached between Grumman and MSC propulsion personnel concerning the Propulsion System Development Facility's test scheduling at White Sands operations in regard to stand occupancy times relating to the ascent and descent development rigs. The tentative schedule showed that the ascent LEM Test Article (LTA)-5 vehicle would not start testing until April 1967. The PA-1 rig prototype ascent propulsion rig) would therefore be required to prove the final design and support early LEMs.
The PA-1 rig was designed and was being fabricated to accommodate small propellant tanks, and there were no plans to update it with larger ones. Therefore, advantages of flexibility, running tests of longer sustained durations, and with the final tank outlet configurations would not be realized. Grumman was requested to take immediate action to have the rig accommodate the larger tanks and install the smaller tanks by use of adapters or other methods.
ASPO requested the Apollo Program Director to revise the LEM control weight at translunar injection as follows:
Systems Engineering Division chief, Owen E. Maynard, reported to the Instrumentation and Electronic Systems Division (IESD) the results of a study on a LEM communications problem (undertaken by his own group at IESD's request). During phases of powered descent to certain landing sites (those in excess of 20 degrees east or west longitude), the structure of the spacecraft would block the steerable antenna's line of sight with the earth. Communications with the ground would therefore be lost. Maynard concurred with IESD that the problem could best be solved by rotating the LEM about its thrust axis.
Grumman advised MSC of major troubles plaguing development of the LEM's descent engine. These included problems of weight, chamber erosion, mixtures, valves, combustion instability, and throttle mechanisms (which Grumman said could delay delivery of LEM 1 and the start of qualification testing).
MSC requested Grumman to review the following ascent and descent pressurization system components in the propulsion subsystem for materials compatibility with certain propellants:
MSC requested that Grumman study the feasibility of a "fire-till- touchdown" landing procedure for the LEM. Grumman was to investigate especially performance factors surrounding crushing of the descent engine skirt, or possibly jettisoning the skirt, and was to recommend hardware modifications required for this landing mode.
Bell Aerosystems Company reported that the LEM ascent engine bipropellant cooled injector baffle met all basic specification requirements, including those for combustion efficiency, ablative compatibility, and stability. Bell conducted a successful firing with an engine that had previously been vibrated to simulate launch boost and lunar descent. The contractor also completed a duty cycle firing at AEDC with hardware conditions set to the maximum temperatures believed attainable during a lunar mission.
The LEM electrical power system use of the primary structure as the electrical ground return was approved after Grumman presentations were made to ASPO and Engineering and Development personnel. The descent-stage batteries would not use a descent-stage structure ground to preclude current flow through the pyrotechnic interstage nut and bolt assemblies. The ascent and descent stage batteries would be grounded to primary structure in the near vicinity of the ascent-stage batteries. In addition, several selected manually operated solenoids would ground. All other subsystems would remain grounded to the "single-point" vehicle ground. This change would be implemented by Grumman with no cost or schedule impact and would effect a weight savings of approximately 7.7 kg (17 lbs).
In reply to a letter from Grumman, MSC concurred with the recommendation that a 135-centimeter lunar surface probe be provided on each landing-leg footpad and that the engine cutoff logic retain its basic manual mode. MSC did not concur with the Grumman recommendation to incorporate the automatic engine cutoff logic in the LM design. MSC believed that the planned descent-stage engine's manual cutoff landing mode was adequate to accomplish lunar touchdown and had decided that the probe-actuated cutoff capability should not be included in the LM design.
MSC Director Robert R. Gilruth requested of Jet Propulsion Laboratory Director William H. Pickering that JPL fire the Surveyor spacecraft's vernier engine after the Surveyor landed on moon, to give insight into how much erosion could be expected from an LM landing. The LM descent engine was to operate until it was about one nozzle diameter from landing on the lunar surface; after the Surveyor landed, its engine would be about the same distance from the surface. Gilruth told Pickering that LaRC was testing a reaction control engine to establish surface shear pressure forces, surface pressures, and back pressure sources, and offered JPL that data when obtained.
Handling and installation responsibilities for the LM descent stage scientific equipment (SEQ) were defined in a letter from MSC to Grumman Aircraft Engineering Corp. The descent stage SEQ was composed of three basic packages:
Donald K. Slayton said there was some question about including extravehicular activity on the AS-503 mission, but he felt that, to make a maximum contribution to the lunar mission, one period of EVA should be included. Slayton pointed out that during the coast period (simulating lunar orbit) in the current flight plan the EVA opportunity appeared best between hour 90 and hour 100. Additional Details: here....
ASPO Manager Joseph F. Shea requested that the White Sands Test Facility be authorized to conduct the descent propulsion system series tests starting April 3 and ending about May 1. The maximum expected test pressure would be 174 newtons per sq cm (253 psia), normal maximum operating pressure. The pressure could go as high as 179 newtons per sq cm (260 psia) according to the test to be conducted.
Required leak check operations were also requested at a maximum pressure of 142 newtons per sq cm (206 psia), with a design limit of 186 newtons per sq cm (270 psia). The test fluids would be compatible with the titanium alloy at the test pressures. The test would be conducted in the Altitude Test Stand, where adequate protection existed for isolating and containing a failure. MSC Director Robert R. Gilruth approved the request the same day.
C. H. Bolender, ASPO Manager for the lunar module, wrote Joseph G. Gavin, Jr., Grumman LM Program Director, that recent LM weights and weight growth trends during the past several months established the need to identify actions that would reduce weight and preclude future weight growth. Additional Details: here....
ASPO Manager George M. Low discussed with Rocco Petrone of KSC the problem of high humidity levels within the spacecraft-lunar module adapter. Petrone advised that several changes had been made to alleviate the problem: air conditioning in the SLA and the instrument unit would remain on during propellant loading; and the rate of air flow into the SLA was increased. Also, technicians at the Cape had designed a tygon tube to be installed to bring dry air into the LM descent engine bell, should this added precaution prove necessary. With these changes, Low felt confident that the humidity problem had been resolved.
Grumman President L. J. Evans wrote ASPO Manager George M. Low stating his agreement with NASA's decision to forego a second unmanned LM flight using LM-2. (Grumman's new position - the company had earlier strongly urged such a second flight - was reached after discussions with Low and LM Manager G. H. Bolender at the end of January and after flight data was presented at the February 6 meeting of the OMSF Management Council.) Although the decision was not irreversible, being subject to further investigations by both contractor and customer, both sides now were geared for a manned flight on the next LM mission. Additional Details: here....
The LM Descent Engine Program Review was held at TRW Systems, Redondo Beach, Calif., reviewing the overall program status, technical and manufacturing problems, and program costs. Program status reports showed that 28 engines had been delivered in the LM descent engine program to date, including all White Sands Test Facility engines and engine rebuilds and all qualification test and flight engines; 9 WSTF engines and 12 flight engines remained to be delivered. Grumman indicated all engine delivery dates coincided with the vehicle need dates.
ASPO Manager George M. Low and others from MSC met with Grumman's LM engineering staff, headed by Thomas J. Kelly, to discuss the descent stage heatshield and thermal blanket problems associated with reduced thrust decay of the descent engine at lunar touchdown. Additional Details: here....
The Allison descent-stage propellant tank, being redesigned at Airite Division of Sargent Industries to a "lidless" configuration, blew up during qualification test at Airite. The crew noticed loss of pressure and therefore tightened fittings and repressurized. As the pressure went up, the tank blew into several pieces. Grumman dispatched a team to Airite to determine the cause and the necessary corrective action.
Howard W. Tindall, Jr., Chief of Apollo Data Priority Coordination within ASPO, reported an operational system problem aboard the LM. To give a returning Apollo crew an indication of time remaining to perform a landing maneuver or to abort, a light on the LM instrument panel would come on when about two minutes worth of propellants remained in the descent propellant system tanks with the descent engine running at 25-percent thrust. The present LM weight and descent trajectory were such that the light would always come on before touchdown. The only hitch, said Tindall, was that the signal was connected to the spacecraft master alarm. "Just at the most critical time in the most critical operation of a perfectly nominal lunar landing mission, the master alarm with all its lights, bells, and whistles will go off." Tindall related that some four or five years earlier, astronaut Pete Conrad had called the arrangement "completely unacceptable . . . but he was probably just an Ensign at the time and apparently no one paid any attention." If this "is not fixed," Tindall said, "I predict the first words uttered by the first astronaut to land on the moon will be 'Gee whiz, that master alarm certainly startled me.'" Tindall recommended either rerouting the signal wiring to bypass the alarm or cutting the signal wire and relying solely on the propellant gauges to assess flight time remaining.
The MSF Management Council, meeting at KSC, agreed that MSC would take the following actions for augmenting the capability of the Apollo system to accomplish a successful lunar landing mission and for planning further lunar exploration:
In a report to the Administrator, the Associate Administrator for Manned Space Flight summed up the feeling of accomplishment as well as the problem of the space program: "The phenomenal precision and practically flawless performance of the Apollo 9 lunar module descent and ascent engines on March 7 were major milestones in the progress toward our first manned landing on the moon, and tributes to the intensive contractor and government effort that brought these two complex systems to the point of safe and reliable manned space flight. Additional Details: here....
MSC appointed a panel to investigate a February 13 accident at the Aerojet-General plant in Fullerton, Calif., that had damaged a lunar module descent tank beyond repair. Panel findings were reported to a review board later in the month, which recommended needed safety measures.