Born: 1911.
Kamanin has his first face-to-face meeting with Korolev in 3 months - the longest delay in three years of working together. Their relationship is at low ebb. Despite having last talked about the next Voskhod flight by the end of November, Korolev now reveals that the spacecraft are still incomplete, and that he has abandoned plans to finish the last two (s/n 8 and 9), since these would overlap with planned Soyuz flights. By the first quarter of 1966 OKB-1 expects to be completing two Soyuz spacecraft per quarter, and by the end of 1966, one per month. Voskhod s/n 5, 6, and 7 will only be completed in January-February 1966. Korolev has decided to delete the artificial gravity experiment from s/n 6 and instead fly this spacecraft with two crew for a 20-day mission. The artificial gravity experiment will be moved to s/n 7. Completion of any of the Voskhods for spacewalks has been given up; future EVA experiments will be conducted from Soyuz spacecraft. Korolev says he has supported VVS leadership of manned spaceflight in conversations with Tyulin, Afanasyev, Pashkov, and Smirnov.
Gemini 7 has the space flight duration record, and Gemini 6 has achieved the first rendezvous in orbit. Yesterday Pashkov sent a letter to Smirnov, asking that new series of Voskhod spacecraft be ordered as insurance in case of further delays in development of the Soyuz spacecraft. Kamanin believes he sees panic setting in with the leadership. The next day Kamanin attempts to call Korolev, only to find he is out sick.
Smirnov calls the Military Industrial Commission and the Chief Designers together to consider Pashkov's letter and how to respond to the American Gemini successes. Korolev is ill and unable to attend. His deputies are unable to provide any firm schedule for completion and fight of Voskhod or Soyuz spacecraft. Soviet projections are that over the next year the Americans will fly manned missions of 20 to 30 days duration and conduct many military experiments from manned spacecraft. It is decided that a crash effort needs to be applied to Soyuz development. However no further Voskhods will be built beyond the five already being assembled, but those Voskhods will be dedicated to setting record duration flights of 15 to 30 days and conducting military experiments.
While Gemini 11 orbits above, the Soviet leadership argues about fundamental organisational details. Pashkov leads a meeting of the VPK, with Litvinov, Kerimov, Pravetskiy, Tregub, Tsarev, Bogdanov; Rudenko, and Moroz present. After prolonged debate, it is decided that Kiyasov, Kerimov and Kamanin will prepare a letter to the Central Committee. The TsPK Cosmonaut Training Centre will remain the only such centre in the country. However the VVS will agree to some modifications in existing selection and training arrangements. The Ministry of Public Health will be excluded from participation in selection and training of cosmonauts.
Rudenko has reached agreement with Mishin that L1 and L3 crews will also consist of a VVS pilot as commander, and an OKB-1 flight engineer. Kamanin is depressed. Despite the support six marshals (Malinovskiy, Grechko, Zakharov, Krylov, Vershinin and Rudenko), Mishin has won this argument with the support of Ustinov, Serbin, Smirnov, Pashkov, Keldysh, Afanasyev, and Petrovskiy. Later the State Commission meets, for the first time in a long time at Tyuratam. Kerimov chairs the session, with more than 100 attendees, including Mishin, Rudenko, Krylov, Pravetskiy, Kurushin, Ryazanskiy, Mnatsakanian, and Tkachev. All is certified ready,. Launch of the active spacecraft is set for 26 November, and the passive vehicle on 27 November.
The booster was supposed to be launched by 1966, but there is no way it will be finished this year, and it is highly questionable it will even get off the ground in 1968. The N1 tanks are pressurised to 2 atmospheres, and can go up to three atmospheres in an emergency. In the enormous MIK assembly hall are three N1's - one 'iron bird' ground test model and two flight vehicles. The first roll out of the mock-up will take place in 1967, and the first launch attempt is still expected in 1968 (the first launch will not be attempted until the second and third stages complete stand tests. There is no test stand for the first stage, it will be fired for the first time in flight). An explosion would destroy the pad, requiring several years of repairs. There are two pads, but even that would not be a guarantee of the availability of the rocket due to the poor expected initial reliability. The N1 project is costing 10 billion roubles, not including considerable investment required by the military. To Kamanin the whole thing is a boondoggle, showing the necessity for development of lighter air-launched boosters. He believes there are many mistakes in design and construction, but Mishin, Pashkov, Smirnov, and Ustinov support these doubtful projects of Korolev and Mishin, instead of technically sound projects such as Chelomei's UR-700 or MiG's air-launched spacecraft. If Mishin thinks the current Proton/L1 reliability is only 0.6, then that of the completely unproved N1/L3 must be even less...
The first Saturn V and Surveyor 6 have been launched by the Americans. Kamanin catalogues why the Americans are beating them: bad organisation, on the parts of Ustinov, Smirnov, Pashkov, Malinovskiy, and Grechko; technical errors and an undisciplined approach to the fulfilment of government decrees concerning the Soyuz and N1 on the parts of Chief Designers Korolev and Mishin; lack of coordination between the institutes and design bureaux compared to the United States; and finally, the Americans are spending several times more money than has been dedicated to the Soviet space program.
Kamanin attends an Almaz program review with Pashkov, Afanasyev, and Chelomei. The resolution of June 1967 required space trials to begin in 1968, and entry of the system into military service in 1969. But this schedule was flawed from the beginning. The project plan required design, qualification, and delivery of completely new complex systems from ten different ministries. The Ministry of Radio Equipment was to deliver 66 items, but the ministry refused, saying they could handle two at most. Similar responses were received from other ministries. The result is that six months into the program, the first flight schedule has already slid 24 months, to 1970. The VVS has been dealing with Chelomei for two years, and find him much better to work with than Mishin. Chelomei's deputies are highly cultured men, pleasant to work with (unlike Mishin and his circle). The VVS is to handle the following on the Almaz program:
Kamanin is dumbfounded. The leadership has decided to accept Mishin's recommendations, scrap the 7K-VI project, and replace it with a Soyuz variant! Mishin is an egotist, but he is supported by highly-placed leaders - Ustinov, Smirnov, Pashkov, Serbin, Stroganov, Keldysh, and others. So everyone in the space program has to dance in the service of this 'engineer-performer', who is not a credible chief designer.
Apollo 8 has been launched. Kamanin recalls that he first saw a model of the Saturn V during his visit to Washington DC with Titov in 1962. At that time the Soviet Union planned to fly the N1 in four years, but the only manned spacecraft on the drawing boards after Voskhod was the Sever. Khrushchev didn't give a go-ahead for the lunar program until 1964. In the gap between Voskhod and Soyuz flights, when the American Gemini program seized the lead, the USSR could have achieved a record by flying Volynov for 18 days in Voskhod 3. But this was cancelled at the last minute by the leadership because the Voskhod had 'no development potential'. Ustinov, Smirnov, Pashkov were responsible for this decision, which put the USSR permanently behind in the space race.
After two days of snow, family, and rest at this dacha, Kamanin is called to a General Staff meeting - the issue - how to answer the Americans? Attending are Generals Kutakhov, Moroz, Ponomarev, Kustanin, Yoffe, Frolov, Kartakhov, and others. It is agreed that the only proper answer is a Soviet lunar landing - but that is two to three years away. The 1964 resolution authorising the lunar program required a lunar flyby to be conducted by 1967 and a landing by 1968. But Ustinov, Serbin, Smirnov, and Pashkov hindered the attainment of this order. They were always requiring meetings, analyses, reports. The result - now many volumes of reports, but no action. The VPK proposes to land a Ye-8-5 robot on the moon and return lunar soil to earth in a 50 cm diameter, 38 kg capsule. The capsule will descend under a parachute and transmit on two VHF beacons in order to be located. But this still does not exist in metal, just in mock-up form. Considered logically, it could not be available earlier than the second half of 1969. The existing schedule for it to fly in the first half of the year is illogical and unachievable. Kamanin looks back with bitterness on the year of 1968 -- they have lost the moon race, they have lost Gagarin. His only consolation is his family.
Mishin, Keldysh, Pashkov, Smirnov, and Serbin meet. Some of them are still expecting a big failure in the Apollo programme that will set the Americans back and still make it possible for Russia to be first on the moon. These are black days in the Soviet programme - it is clear to Kamanin that the Americans will successfully land on the moon in July, and the Russians are 2 to 3 years behind.
Over two days a State Commission reviewed all of the conclusions of the N1 3L failure investigation and the readiness of N1 5L for flight. All of the fixes identified to remedy the 3L failure had been incorporated into 5L. It was felt that the behaviour of the systems in fire conditions were understood and appropriate measures had been taken. The wiring had been rerouted and insulated. Barmin wanted the system not to shut down any engines under any conditions during the first 15-20 seconds of flight, so that the booster would clear the pad and there would be no risk of the pad's destruction. But there was no time to develop such measures before the 5L launch; it could only be added in vehicle 6L. Additional Details: here....
Meeting of Kamanin with S G Donevskiy. The L3 trainer will not be finished until May 1970 - and the current schedule for the first manned L3 launch is December 1970! But in any case Kamanin assesses the latter date as unrealistic -- there is no rocket or spacecraft in being yet. Later in the day Efimov, Moroz, and Kamanin meet with the female cosmonauts - Ponomaryova, Solovyova, Yerkina, and Kuznetsova. They advise them that despite the letter to the Central Committee asking for an all-female Soyuz flight, it has been rejected. Ustinov, Smirnov, and Pashkov are all opposed to the idea, as are MOM, MAP, AN, and VVS. Kamanin believes the whole female cosmonaut concept was a mistake. Flying Tereshkova in the first place started the whole thing, but now there is no follow-up.